Park County Public Works will provide regular updates regarding road projects and maintenance taking place across the county.
Special Projects
Elkhorn (CR15)
Project Overview: CR15 also known as the Elkhorn or Elkhorn Road, number of miles, describe why we are doing this
Updates: The county gave the contractor a final checklist to complete on July 22, 2024. They completed the final checklist and the county signed off on the project on July 31st, 2024. A final packet for the project is being put together to be released to the public and encompasses the entire project scope.
Timeline: Project successfully completed on July 31, 2024.
11-Mile Road Reclamation
Project Overview: Improvements focus on: CR59, CR92, and CR90. Roads will be getting 2 inches of new road base milled in with 2-4 inches of existing chip seal and base. Mag chloride will be mixed in throughout the new and existing material to create a solid road base.
Updates: CR59, CR92, and CR90 will be getting 2 inches of new road base milled in with 2-4 inches of existing chip seal and base. Mag chloride will be mixed in throughout the new and existing material to create a solid road base. CR59 has been re-graded for proper crown and drainage.
The contractor has completed roughly 6 miles of CR92 from the Chaparral General Store to the 11-Mile State Park Marina. The contractor is running their reclaimer that mills up the road base about a mile per day and is catching up to road base that was laid last week. They will begin final grading on CR92 and will be applying a top shot of magnesium.
Timeline: The project began in May 2024 and is scheduled to conclude in September 2024.
Road Grading and Maintenance Updates by District
County-Wide Work
- Flood and emergency repair due to storms and runoff
- Code Red Call Outs
- 78,560 gallons of Mag Chloride
- 67,000 tons of gravel placed
- 437 road miles graded
District 1
- CR58, 60, 68, Burland Ranch, Friendship Ranch, Delwood
- Potholes – 115-ton asphalt
District 2
- CR35,7 ,56 ,33 ,54 ,439, Buffalo subdivision, Arrowhead, Apache, Ute trace, Fitzsimmons
- Potholes – 45 tons asphalt
District 3
- CR23, 53,102, Chaparral Road, 104,59,88
- Potholes -147 tons asphalt
District 4
- Ranch of the Rockies, Foxtail pines, Coil Placer, 6, Lower 4, 12,14,18
- Potholes – 60 tons asphalt
General Updates and Reminders
- Working hours are 7 a.m. to 7 p.m. Monday to Friday
- Signs and construction devices will be present to alert the public to the closures and alternate routes
- Construction schedules are weather dependent and subject to change